The energy ministry must be glad for the current media focus
on the Office of the Prime Minister and the public service ministry.
The daily revelations about the massive hemorrhaging of tax
payers’ money into the pockets of a handful of officials had us all riveted
that we missed the ruling two weeks ago by the civil division of the high
court.
The issue was the ruling on an application for a judicial
review of the tendering process to construct the 700 MW Karuma power dam in
northern Uganda.
In October, frustrated by the tender process and suspicious
that the energy ministry officials had contrived to award the contract to
another bidder China International Water & Electric Corporation (CWE),
Salini S.p.A applied for a judicial review of the process.
So on November 16th high court justice Eldad
Mwangusya delivered his ruling.
But first some background.
The $2.2b Karuma Dam is going to be the biggest single
investment project in the country’s history. Bids were opened in November last
year and according to the time line the winning contractor was to take
possession of the site in March. The project was supposed to take six years to
completion.
Inexplicably the evaluation process took long, bursting the
original timelines. Then rumours begun to fly of money changing hands and that
the process had been short circuited and the contract awarded anyway to the CWE.
Several of the bidders called for an administrative review of
the process – which entails going over the way the process had been handled,
but realizing that energy ministry officials were hell bent on the awarding the
contract they resorted to the courts.
In the application for a judicial review Salini sought to have
the court pronounce itself on eight issues whose net effect was to find that
procurement rules had been flouted and to hold the attorney general and the
executive director of the government’s procurement agency (PPDA) responsible,
to call for a reevaluation of the bids by independent evaluators.
Short and long of it Justice Mwangusya ruled in Salini’s
favour on all but one ground.
This of course further delays the Karuma further and at the
rate at which we are going it will be a miracle if construction begins before
the next budget.
But the most jaw breaking part of the ruling was in
reference to a letter written by the attorney general to the CWE General
manager.
The letter “Stated among other things that the bidder should
state the terms and conditions that should be included in the contract. This
actually means that the contract has already been awarded to this bidder yet
the procurement process is still ongoing,” Mwangusya said.
He said this was contrary to the PPDA act adding that, “The
very essence of the statute has been frustrated by the persons that are
mandated to safeguard it.”
The background to this letter to CWE was a meeting that was
held with President Yoweri Museveni on August 14 where the energy minister
Irene Muloni, her junior minister Simon D’Ujunga, the ministry’s permanent
secretary Kaliisa Kabagambe, Attorney General Peter Nyombi presented CWE
officials to Museveni.
In the meeting it was agreed that CWE presents guarantees
from its parent company China Three Gorges Corporation in order to get the
contract, a request that was irregular in that no other bidder was asked for a
guarantee. Why it was necessary for CWE to provide a guarantee is another story.
A lot of deals have gone down in this town, many of which we
have never been privy to, but August 14th will have pride of place
as one of the darkest days
in Uganda’s history.
What was happening in this meeting? Was the president made
aware that the meeting with a bidder in an ongoing process was a flouting
regulations? Did he know that the meeting in offering remedies to CWE’s bid
would be detrimental to the process? What did the relevant ministers and
technocrats seating in the meeting advise?
“It is trite law that an illegality once brought to the
attention of the court cannot be ignored,” Justice Mwangusya said in reaction
to the letter that came as a result of that meeting.
The addition of Bujagali’s power onto the grid earlier this
year has removed the urgency for more power to alleviate loadshedding. However
it is expected that new demand will suck up all his new power within the next
18 months sending us back to the days of loadshedding.
Officials have been heard to mutter that it is bidders
running to court that are frustrating the process, but on the other hand if
such blatant disregard of procedure were not there what grounds would there be
for appeal. This is not the first tender we are doing in this country.
In more cultured society somebody should be stepping down,
getting fired or worse, but then again what do I know?
No comments:
Post a Comment