As of writing this column Umeme’s 20 year concession will come to a close today Monday, 31st March.
Last week the Auditor General submitted his final report
putting what the government owes to Umeme as a final pay out at $118m, below any
previous estimates. According to Umeme the government owes them $234m,
previously the Auditor General had estimated the payout at $201m, while Electricity
Regulatory Authority (ERA) the overseer of the concession had put their figure
at $127m.
The payout is compensation for assets not fully paid for
through the tariff.
It was curious how the discrepancies between all the players
were so wide and I guess this will be resolved in the fullness of time.
It has been an interesting journey and a test case for the management
of such Private Public Partnerships (PPP), as we will probably need to do more
of in the future.
At the tail end of the privatization process, at the end of
1990s, the big infrastructure companies like Uganda Electricity Board (UEB) and
Uganda Posts & Telecommunications Corporation (UPTC) came up for sale.
Unlike previous privatisations for which it was enough to liquidate,
sell their assets or sell them as is, these companies demanded different
treatment.
In the case of UEB a total overhaul of the electricity
sector was required to attract funding into the sector.
"For starters the tariff had to be raised, as the prevailing
tariff, around US4cents a unit at the time, did not allow for the sector to be run sustainably,
leave alone promise a return for intending investors...
Critical too to the reforms was the breakup of UEB into its
constituent parts – generation, transmission and distribution. This was done
because it was easier to get investment for parts of the company rather than
the whole. As has proved true.
Billions of dollars in investment have been sourced by government
and private players in the generation and distribution sector. Government has
had to follow suit with comparable investment in the transmission part to keep
up with new interest up and down stream.
Umeme came in at a time when we were suffering day long
power cuts and as if that was not enough, around that time the water levels on
Lake Victoria fell dramatically, affecting power generation at the
Kiira-Nalubale power station.
Government opted for expensive thermal power, which raised
tariffs even higher and saddled government with trillions of shillings in
subsidies to the sector to keep the power tariff manageable for the paying
public.
It is only when Bujagali came on line 2012, with the sector
seeing surplus generation capacity for the first time in decades, eliminating loadshedding, did Umeme really take off. It should be noted that Bujagali’s commissioning was
delayed almost 10 years as politicians and environmentalists threw roadblocks
at every turn of its development.
With increased generation Umeme had to ramp up the last mile
distribution grid, accelerating account numbers to around two million currently
from the 300,000 they inherited.
Of course once it is done everybody jumps up and says it was
not that difficult after all, anyone could have done it.
But there certain key things that allowed Umeme to do what
UEB could not do.
For starters the managers of Umeme were only dealing with
one part of the electricity chain, albeit the crucial one, because if Umeme was
not paid transmission and generation would not have been paid. It should be
noted that the installation of yaka in 2011, which Umeme were initially
reluctant to undertake, because of the huge initial capital outlay, has with a
single stroke increased billing to almost 100 percent.
In addition the higher tariff Umeme has enjoyed has allowed them to not only
maintain the grid but expand it almost five fold during the concession to 70,000
km from the 16,000 km they inherited.
Secondly, Umeme has been able to invest almost $800m over the last 20 years, because on the strength of the balance sheet, go to the market to source funding, and not rely on treasury for funding. This was critical for speed of execution of many of its programs...
It helped too that with increased digitization greater
efficiencies have been enjoyed that UEB could only dream about. Though on the
other hand the profit motive can be a strong incentive to push innovation and
early adoption of new technologies.
Unfortunately the concession seems to have come to an acrimonious
end. But the management of Umeme can leave l knowing they have set bar against
which its successors will be measured. Umeme may have benefitted from being
measured against the low bar of UEB, the same will not be the case for its
successor.
No comments:
Post a Comment